What Is FAT vs SAT in Transformer Procurement?
FAT
Run at the factory, it verifies the design and the unit against the specification — tests, losses, quality, documentation — and any changes are made before it leaves.
SAT
Run on site after installation, it confirms correct erection, connections, protection settings, auxiliary/cooling operation and that the unit passes the pre-commissioning checks before energisation.
Witnessing
FAT is often witnessed by the customer (or an inspector) for the agreed tests; SAT is witnessed on site and may include a period of supervised energisation.
References & standards
- IEC 60076-1
- IEEE C57.12.90
Related
Related manufacturers
Acme Electric (Hubbell) · Central Moloney · CORE Transformers · Daelim Transformer (US) · Delta Star · Eaton
Related components
Travelling for a factory acceptance test (FAT)
Engineers attending a factory acceptance test or a site visit often need travel insurance and a data eSIM. The provider sets the price. TransformerPath does not quote a premium or a data plan.
Travel tools for engineers on a FAT or site visit. Affiliate disclosure. TransformerPath does not set prices.
Submit an RFQ or browse manufacturers and components.
Submit an RFQ Get Verified