400 kV Choczewo–Żarnowiec line (offshore wind connection)
A Construction transformer-relevant grid/substation project, tracked as an entity (not an article) by TransformerPath.
INFERRED Transformer requirement is reasonably inferred from the substation / grid scope.
Project record
| Project | 400 kV Choczewo–Żarnowiec line (offshore wind connection) |
|---|---|
| Region | Europe |
| Country | Poland |
| Utility / buyer | PSE (Polskie Sieci Elektroenergetyczne) |
| EPC | Elbudbis (line construction) |
| Transformer requirement | INFERRED |
| Voltage | 400 kV |
| Status | Construction |
| Expected | — |
Sources
- PSE press release · source
Market context
Market hub not yet built.
Last reviewed: 2026-09-01. Sources: public tender/project announcements and TransformerPath Daily Intel; transformer scope graded per the CONFIRMED / INFERRED / UNKNOWN taxonomy. Report a correction.
Supply this project
Submit a transformer requirement and TransformerPath will match it against the relevant manufacturing base.