Nueva Línea HVDC Kimal – Lo Aguirre 500 kV
A Construction transformer-relevant grid/substation project, tracked as an entity (not an article) by TransformerPath.
INFERRED Transformer requirement is reasonably inferred from the substation / grid scope.
Project record
| Project | Nueva Línea HVDC Kimal – Lo Aguirre 500 kV |
|---|---|
| Region | Latin America |
| Country | Chile |
| Utility / buyer | Conexión Kimal–Lo Aguirre (consorcio ISA + Transelec + China Southern Power Grid) |
| EPC | ESINEL (ingeniería y diseño civil, Tramo N3) |
| Transformer requirement | INFERRED |
| Voltage | 500 kV HVDC |
| Status | Construction |
| Expected | 2029 |
Sources
Market context
Market hub not yet built.
Last reviewed: 2026-09-01. Sources: public tender/project announcements and TransformerPath Daily Intel; transformer scope graded per the CONFIRMED / INFERRED / UNKNOWN taxonomy. Report a correction.
Supply this project
Submit a transformer requirement and TransformerPath will match it against the relevant manufacturing base.